Faizabad HEPP

Faizabad HEPP Hydro Electric Power Plant bringing employment opportunities & renewable energy to Faizabad, Afghani Please feel free to contact us for information.

Faizabad Hydro Electric Power Plant is bringing employment opportunities & renewable energy to Faizabad, Afghanistan. This page is for the local community of Faizabad, to keep you up to date & informed on all progress & issues relating to Faizabad Hydro Electric Power Plant. We will be posting in both English & Dari. Like us for regular updates and pictures. Account run by Shorsec Consulting Ltd. [email protected]

Today, on 28 May 2021, the Taking-Over Certificate was issued so that the hydropower plant is now available for commerci...
28/05/2021

Today, on 28 May 2021, the Taking-Over Certificate was issued so that the hydropower plant is now available for commercial operation. DABS will hand over the project to the Government of the Islamic Republic of Afghanistan who has awarded a concession to Badakhshon Energy Company to operate the project for 30 years. 🤩
امروز 28 ماه می 2021 سند دوره تسلمی پروژه به امضا رسید فلهذا بند برق آماده تولید انرژی است. ریاست برشنا پروژه را به شرکت بدخشان انرژی تسلیم خواهد داد و شرکت بدخشان انرژی برای مدت 30 سال مسولیت عملیاتی بند برق را به عهده دارد.

The reservoir has now been filled again so that the turbines can be tested under operating conditions. These tests are s...
03/05/2021

The reservoir has now been filled again so that the turbines can be tested under operating conditions. These tests are scheduled to be completed by mid-May when the plant will be handed over to DABS.
آب گیری بند برق دوباره انجام شد و حالا میتوان توربین ها را در حالت گردش تست کرد. نظر به تقسیم اوقات این تست ها در میانه ماه می سال جاری تکمیل میگردد و بند برق به شرکت برشنا تسلیم داده خواهد شد.

Testing and commissioning is scheduled to commence within the next two weeks. 😀 When commissioned, the electricity will ...
01/04/2021

Testing and commissioning is scheduled to commence within the next two weeks. 😀 When commissioned, the electricity will be finally ready for Faizabad!
مطابق تقسیم اوقات تست و کمیشنینگ در دو هفته آینده آغاز میشود. بعد از ختم کمیشنینگ بلاخره فیض آباد از نور برق مستفید خواهد شد.

Finally, on 21 February, the stators for the generators arrived so that the generators are now being installed and elect...
01/03/2021

Finally, on 21 February, the stators for the generators arrived so that the generators are now being installed and electricity will be generated as soon as possible. 🤩
بلاخره در تاریخ 21 فبروری دینامو های جنراتور در ساحه رسید و جنراتور ها در حال نصب شدن هستند به زودترین فرست تولید برق ممکن است.

The reservoir was recently filled to its full supply level for the first time. After suffering a prolonged delay at cust...
01/02/2021

The reservoir was recently filled to its full supply level for the first time. After suffering a prolonged delay at customs, the first generator parts have been delivered to the site with the remainder expected in February and first electricity generation possible in some months.😃
برای اولین بار بند برق شورآبک به سطح حد اکثر آب گیری گردید.بعد از تاخیری در گمرک بخش اول وسایل جنراتور ها به فیض آباد انتقال یافت و باقی مانده وسایل جنراتور ها در همین ماه فبروری انتقال خواهد گردید و در ماه های آینده تولید برق امکان پذیر است.

After being held in customs in Karachi for four-and-a-half months, the generators are now on their way to Faizabad.🤩 جنر...
04/01/2021

After being held in customs in Karachi for four-and-a-half months, the generators are now on their way to Faizabad.🤩
جنراتور ها بعد از سپری نمودن چهار و نیم ماه در گمرگ کراچی پاکستان فعلا به طرف فیض آباد در حال انتقال هستند.

The photos show recent work in progress on the site 🙂تصاویر جریان پیشرفت کار را در ساحه نشان میدهد.
21/12/2020

The photos show recent work in progress on the site 🙂
تصاویر جریان پیشرفت کار را در ساحه نشان میدهد.

The photos of recent work on the site show good progress on these impressive structures in winter conditions.قسمیکه در ت...
30/11/2020

The photos of recent work on the site show good progress on these impressive structures in winter conditions.
قسمیکه در تصاویر مشاهده میکنید کار در سرما زمستان در حال پیشرفت است.

More than 90% overall progress now achieved with the powerhouse getting a nice architectural finish and electrical and m...
16/11/2020

More than 90% overall progress now achieved with the powerhouse getting a nice architectural finish and electrical and mechanical balance of plant (EBoP and MBoP) being installed inside 🤩
با نصب نمودن وسایل میخانیکی الکتریکل و کار های معماری در داخل پاورهوس بیشتر از 90 فیصد کار ها انجام یافته.

Good progress continues with excellent quality both inside and outside the powerhouse.😃کار ها در داخل و خارج پاور هوس با...
02/11/2020

Good progress continues with excellent quality both inside and outside the powerhouse.😃
کار ها در داخل و خارج پاور هوس با کیفیت خوب و عالی در حال پیشرفت است

High quality work continues at a good pace both inside and outside the powerhouse.کار ها در داخل و خارج از پاور هوس با س...
19/10/2020

High quality work continues at a good pace both inside and outside the powerhouse.
کار ها در داخل و خارج از پاور هوس با سرعت و کیفیت عالی پیش میرود.

Completion would be in the first quarter of 2021, if the generators can be released from the port of Karachi now. 🤞Requi...
05/10/2020

Completion would be in the first quarter of 2021, if the generators can be released from the port of Karachi now. 🤞Requisite paperwork from Kabul is still awaited to get the generators released in Karachi. Big problem!🙀
اگر جنراتور ها از گمرگ کراچی پاکستان خارج شوند احتمال دارد کار پروژه در ربع اول سال 2021 تکمیل شود. منتظر طی مراحل اسناد بخاطر خارج ساختن جنراتور ها از کراچی هستیم ....... مشکل بزرگ.